Slnc schreef op 14 juli 2019 23:13:
[...]
weet niet precies wat je bedoelt met 9 t/m 17 maar dat ze klokje rond werken is standaard doen ze normaal 5 dagen maar ook soms 6 of 7 dagen in de week
dit komt uit Q1 trading update
We have started our work for Seamade and continued working on Triton Knoll and Borssele 3&4.
For Sif, the Seamade and Triton Knoll projects together constitute 130 Kton of steel, or the
equivalent of 148 monopiles and 58 transition pieces. From the third quarter onwards, we will also
initiate works on Borssele 1&2. After ramping up in Q2, we will then be back on more normalized
quarterly production levels of close to 60 Kton, to end the year with total production numbers of
approximately 210 Kton or 272 monopiles and 150 transition pieces.
Investments in coating facilities are on schedule for completion in July 2019, as is the buildup of our
workforce. To deliver the estimated production volumes,
we will partially lift the option to work 24
hours, seven days a week, at some production points, between the end of Q2 2019 and the end of
the year. With a full order book for 2019 and a sound funnel of projects for the years thereafter, we
are well placed to contribute to the planned growth of the offshore wind industry, both in Europe
and emerging markets in Asia and the north-eastern USA. We are negotiating exclusively on two
projects and are involved on a non-exclusive basis in all other projects on the market. We feel
confident we are well placed to win our fair share of available projects though given the nature and
characteristics of the industry, exact timing remains difficult to predict.
Sif’s theoretical production capacity is between
200 and 250 Kton (on standard 24/5 factory
hours). Based on these hours, Sif manufactures
approximately four to five monopiles a week.